FFP Missouri 17, LLC; BOST2 Hydroelectric, LLC; Notice Announcing Preliminary Permit Drawing

The Commission has received two preliminary permit applications deemed filed on August 6, 2010, at 8:30 a.m., [1] for proposed projects to be located on the Ouachita River, in Caldwell Parish, Louisiana. The applications were filed by FFP Missouri 17, LLC for Project No. 13824-000 and BOST2 Hydroelectric, LLC for Project No. 13826-000.

On February 22, 2012, at 9 a.m. (Eastern Time), the Secretary of the Commission, or her designee, will conduct a random drawing to determine the filing priority of the applicants identified in this notice. The Commission will select among competing permit applications as provided in section 4.37 of its regulations. [2] The priority established by this drawing will be used to determine which applicant, among those with identical filing times, will be considered to have the first-filed application.

The drawing is open to the public and will be held in room 2C, the Commission Meeting Room, located at 888 First Street NE., Washington, DC 20426. A subsequent notice will be issued by the Secretary announcing the results of the drawing.

Dated: February 10, 2012. Nathaniel J. Davis, Sr.,

Deputy Secretary.

Footnotes

1. Under the Commission's Rules of Practice and Procedure, any document received after regular business hours is considered filed at 8:30 a.m. on the next regular business day. 18 CFR 385.2001(a)(2) (2011).

2. CFR 4.37 (2011).

Loading most recent entriesloading

Feedback